Project’s story is transposing in concrete activities. Here’s how the two implementation steps went:

In the first stage a series of investments were executed, achieving the following degrees of achievement:

  • 67.61% building of the mechanical-biological treatment plant (TMB) in Oradea;
  • Purchase of collection equipment / equipment for Valea lui Mihai sorting station and shredders;
  • construction of 4 transfer stations (Salonta, Beius, Marghita, Sacuieni), 3 sorting stations (Salonta, Beius, Marghita) and 1 temporary storage warehouse (Ştei), the work stage being 53.23%;
  • the closure of 8 non-compliant warehouses, the works to be finalized in January 2017.

In the second stage will be finalized a series of investments/contracts:

  • Construction of TMB station in Oradea and access roads;
  • Construction of transfer stations, sorting stations and temporary storage facility and access roads to them;
  • Closure of 8 non-compliant urban deposits in Oradea, Alesd, Beius, Salonta, Marghita, Sacuieni, Valea lui Mihai and Stei;
  • Provide selective waste collection equipment (5000 bins with a capacity of 120 liters for the collection of biodegradable waste and about 3400 specific containers with a capacity of 1.1 mc, 20.000 domestic composts, 4 containers with the capacity of 24 Mc; 1 prescontainer with the capacity of 15 mc; 6 containers with the capacity of 30 mc; 1 tug truck; 6 waste scrapers from gardens and parks; 160 waste bins with the capacity of 770 l)